- Metering devices for 3 different intake structures supplying the plant
- Feed water supply of an existing reservoir of 350 m³
- Pumping station for raw water
- Raw water pumps: 2 pumps with a rate of 75 m³/h
- Install the CIFEC's Aquaneutra unit for degassing excess CO2
- Install a 10 m³ tank for degassed water
- 2 pumps of 75 m³/h to pump the degassed water
- A granulated activated carbon filtration system: 2 enclosed stainless steel filters
- A limestone filtration system: 2 enclosed stainless steel filters
- Treated water tank of 75 m³
- Chlorine and soda regulator in the treated water tank
- Return of treated water to the existing water tower by means of 2 recirculating pumps with a throughput of 75 m³/h
- Washing water tank : 2 pumps with a flow rate of 215 m³/h
- Cleaning air installation: 1 compressor of 540 Nm³/h
- Settling basin of 100 m³
- All associated electrical, automation, monitoring, supervision equipment and anti-intrusion system
56 Boulevard Denis Papin
53000 Laval
TEL.: +33 (0)2 43 59 13 40